PROPERTY DEVELOPMENTS

ARUNDEL OFFICE PARK EXPANSION:

Pre-construction Stage

  • Design development completed
  • Submission of plans to council to facilitate tendering
  • Pre-purchasing bricks completed and delivered to site
  • Fundraising ongoing
  • Construction to commence in H2 2021

FIRST MUTUAL PARK SOLAR PROJECT

  • EPC agreement finalized and signed
  • Equipment delivered to site
  • Contractor commenced works
  • System commissioning expected by 31 August 2021