First Mutual Properties Limited releases a Trading Update for the 5 months ended 31 May 2021, presented at the Annual General Meeting held on 30 June 2021. Below are excerpts from the presentation:
PROPERTY DEVELOPMENTS
ARUNDEL OFFICE PARK EXPANSION:
Pre-construction Stage
- Design development completed
- Submission of plans to council to facilitate tendering
- Pre-purchasing bricks completed and delivered to site
- Fundraising ongoing
- Construction to commence in H2 2021
FIRST MUTUAL PARK SOLAR PROJECT
- EPC agreement finalized and signed
- Equipment delivered to site
- Contractor commenced works
- System commissioning expected by 31 August 2021